Hello!

Is it possible to visualize in some manner flow parallelism in Gantt chart?

We've not found any possibilities to indicate and visualize using link the fact that more activities are starting contemporarily from another single activity.

So, as you can see proc1 & proc2 both are having the same predecessor.

Moreover, proc1.1 and proc2.1.1 having the same target ("join node").

In your gantt datasource only one integer value for successor is available, the same is for predecessors.

Simply, how must be gantt datasource to riproduce the most common MS Project gannt (see image attached)

Thank you in advance