The GanttView allows you to define a calendar with working times, recurrence and special occasions such as Christmas. However, when you assign a resource (owner) to a task, you can also specify the calendar on the resource. For instance, Robin is working 2 days per week and John 5 days per week.
Is it possible to use such a calendar in the automatic gantt scheduling, especially when there is exactly one resource per task assigned?
Hello Guido,
I am just checking about the progress of this issue. Let me know if you need my further assistance on it.
Thank you for using Infragistics Components.
Right now UltraGanttView does not support such functionality. After working on this and doing some research, the idea UltraGanttView to schedule automatically the tasks per resource has been determined to be a new product idea. You can suggest new product ideas for future versions (or vote for existing ones) at <http://ideas.infragistics.com>.
There are many benefits to submitting a product idea:
Direct communication with our product management team regarding your product idea.
Notifications whenever new information regarding your idea becomes available.
Ability to vote on your favorite product ideas to let us know which ones are the most important to you. You will have ten votes for this and can change which ideas you are voting for at any time.
Allow you to shape the future of our products by requesting new controls and products altogether.
You and other developers can discuss existing product ideas with members of our Product Management team.
Steps to create your idea:
Log into the Infragistics Product Idea site at http://ideas.infragistics.com (creating a new login if needed).
Navigate to the product / platform channel of your choice (e.g. WPF, Windows Forms, ASP.NET, HTML5 / Ignite UI, iOS / NucliOS, etc.)
Add your product idea and be sure to be specific and provide as much detail as possible.
Explain the context in which a feature would be used, why it is needed, why it can’t be accomplished today, and who would benefit from it. You can even add screenshots to build a stronger case. Remember that for your suggestion to be successful, you need other members of the community to vote for it. Be convincing!
Include a link to this thread in your idea so product management will be able to look back at this case.
The Product Idea site puts you in the driver’s seat and allows you to track the progress of your ideas at any time, see how many votes it got, read comments from other developers in the community, and see if someone from the product team has additional questions for you.
Thank you for contacting Infragistics.