Is there a way to control whether a milestone should be visible on the begin of the primary interval or on the end?
In case I have a milestone on 31-12 and my primary interval is one month, the milestone is placed on the begin of december. Instead I would like to see it on the end of the interval.
Maybe the other item in this forum "Show exact timeline length having a Months/Weeks primary interval" will also solve my question, but in the mean time I would like to see some temporary solution...
Hello Oskamf,
We are still following your forum thread.
Please feel free to let us know if you still need any further assistance with it.
The Constraint is not solving my issue. The problem is not that the date is wrong, but that the optically location in the diagram is wrong:
The two milestones above have as date 31-12, but are shown on the beginning of december. The grouptask just above them end at the 31th also. The deadlines on the grouptask are shown correctly... Is it possible to get the milestones shown at their correct location?